Concrete Calculator

Estimate concrete for rectangular pours and round columns, subtract void volumes, add allowance, and round a bulk order or bag count using your supplier’s stated yield.

Pour dimensions and purchase model

Runs in your browser

Use non-overlapping shapes. Each row has its own depth and repeat quantity. Deduction volumes are subtracted from the combined total, not located inside a drawing. Changing plan or depth units clears the affected dimensions.

Bulk order rounding

Order rounds upward to a whole multiple of your increment. This is not a supplier minimum order, truck capacity or delivery schedule.

Optional cost — editable price, delivery and tax assumptions

Material subtotal rounds half-up to cents, then material tax rounds once to cents. Delivery is added without tax, even for a zero-volume order. No minimum charges, labor, equipment, fees or exchange rates are included.

Quantity planning only: no structural thickness, strength, reinforcement, foundations, building-code compliance, mixing instructions or load capacity is determined.

Enter your own values to calculate.

Your result appears here

Enter values and calculate. Changing an input clears the previous result.

Inputs stay in this page. Normal assets and visit-statistics requests still occur. Downloads contain the values you entered.

How this calculator works

From pour geometry to a stated purchase quantity

Enter rectangular pours or round columns/cylinders, each with its own depth or height and repeat quantity. Rectangle volume = length × width × depth. Round volume = π × diameter² ÷ 4 × height. Diameter is the full width across the circle, not radius. Circular rows use π ≈ 3.141592653589793. Exact unit definitions and rational arithmetic avoid decimal-conversion drift; they cannot remove measurement or circle-approximation error.

Use separate deduction rows for known void volumes. Net volume = included volume − deductions. Deductions are combined arithmetically, not located in a drawing or checked for overlap. Add an allowance you choose, then choose either bulk order increments or full bags. Multiple rows can model simple parts of a stepped shape, but they must not overlap. Reinforcement, irregular excavation and changes in actual thickness are not measured automatically.

The editable slab example is 10 × 12 feet at 4 inches thick: 40 ft³, or 40/27 ≈ 1.481481 yd³. Adding 10% gives 44 ft³, or about 1.629630 yd³. With 0.25 yd³ bulk increments, round upward to seven increments = 1.75 yd³. Full-order rounding adds extra volume beyond the allowance.

For bags, enter the supplier’s stated finished concrete yield per bag, not the dry bag’s weight or powder volume. If a product states 0.45 ft³ finished yield, the same 44 ft³ requirement needs ceiling(44 ÷ 0.45) = 98 bags, providing a stated 44.1 ft³. The example yield is invented for demonstration; no bag-weight conversion, water amount, cement ratio or material density is inferred.

Optional costs apply to the selected purchase model. At an invented 150.00 per yd³, the 1.75 yd³ order has a 262.50 material subtotal. An entered 8% material tax is 21.00; adding a 75.00 delivery charge gives 358.50. Subtotal rounds half-up to cents first, then material tax rounds once. Delivery is not taxed in this model. Supplier minimums, truck capacities, short-load fees, labor and equipment remain outside the calculation.

Concrete quantity FAQ

Can I use bag weight to calculate finished yield?

No. Product formulations and yields vary. Read the volume of finished concrete per bag on the label or supplier specification and enter it directly. Do not enter powder volume or assume that bags of equal weight produce the same volume.

Does this choose slab thickness, reinforcement or strength?

No. It accepts dimensions you supply for volume arithmetic only. It does not design foundations, determine loads, reinforcement, concrete strength, cover, curing, mix proportions, water additions or compliance with local codes. Appropriate design and site decisions require qualified assessment.

How do voids and circular columns work?

A void row subtracts its calculated volume from the combined included volume; at least one included row is required. Deductions above included volume are rejected. Equal volumes yield no material order, although a fixed delivery charge you entered still applies. For cylinders, enter diameter and height. Rounding near a boundary can depend on the stated π approximation and actual measurements.

Is the allowance a guaranteed sufficient amount?

No. It is a user-selected addition from 0–100%, not a rule for waste, site loss, uneven excavation or supplier tolerance. Bulk orders round to a whole multiple of your chosen increment, not to a supplier minimum. Bags round up to whole bags. Verify the quantity, finished yield, availability and order conditions independently.

What limits, exports and privacy apply?

Use 1–30 rows, positive lengths/diameters up to 100,000 plan units, depths up to 10,000 depth units, and whole repeat counts up to 10,000. Most decimals accept six places; prices/delivery two and tax four. Bulk increment is positive and at most 1,000 order units; stated bag yield is positive and at most 10,000 selected volume units. Included, deducted and purchased volumes are capped at one billion m³, bags at one billion, and total cost at one trillion currency units. CSV/JSON include all rows; JSON preserves calculation fractions, not the exactness of real measurements or π. Inputs stay in this page; normal assets and visit statistics still occur.